Toronto Hospital 24-Hour Emergency Chiller Rebuild
A screw compressor failure in a heatwave, temporary cooling online the same day, and a full compressor rebuild in six days with infection control rules followed throughout.
Seven red-tagged gas appliances repaired, combustion tested and cleared in nine working days, so the warehouse had heat back before the first hard frost.
Repair and Enbridge Red Tag clearance on seven gas-fired heating appliances (suspended unit heaters and RTU gas heat sections) in a Scarborough Junction warehouse after a utility safety inspection.
The Challenge
A utility safety inspection red-tagged seven heating appliances for venting, combustion air and heat exchanger concerns. The warehouse was losing heat going into November, with staff and stock on site.
Our Approach
Results
"They had the scope in writing the same week and every unit cleared before the cold set in. The test sheets satisfied our insurer on the first submission."
Site Photos
More Projects
A screw compressor failure in a heatwave, temporary cooling online the same day, and a full compressor rebuild in six days with infection control rules followed throughout.
24-Hour Commercial Emergency Dispatch
Send the building details and we will walk the site, then give you a written scope, price and schedule.